PHASE0 - SALES 
PROJECT REVIEW
 Review project for feasability  Review project with sales and engineering
brainstorm, Project Risk assessment
APPLICATIONS
 Develop project proposal and estimate  Execute project Applications
Create Worksheet, review specifications
QUOTES
 Finalize project pricing and scheduling Execute Quotation 
Create Quotation, Preliminary Scheduling
SALES REVIEW
 Sell the system  Internal Sales Review and signoff
Sales presentation and closing the SALE.
 
     
     
PHASE1 - ENGINEERING    
KICKOFF PROJECT
 Assign Employees, review specifications  Project Management
Customer relations, Schedule Meeting
PRE ENGINEERING
 Project Review, RoboGuide Simulation  Create RoboGuide Simulation
layout cycle time & reach study
APPROVAL PROCESS
 Review project with customer and sign off  Create Project approval documents
layout, electrical, schedule
ENGINEERING
 Mechanical, Electrical, Software  Create Project engineering documents
layout, Parts, BOM, etc.
Electrical/Mechanical Drawing Set
order long lead items
PHASE2 - SHOP  
FABRICATION
 Fabricate and/or Order Parts, assemble sub assemblies
Verify part drawings
 
RECEIVE COMPONENTS
Check in parts and stage in project bin.  Gather data sheets
 Start sub assemblies
ASSEMBLY
Layout project and set up equipment.  Set up Robot and equipment
Mount EOAT
DEBUG
Install software and debug and test  Install system software
Debug and perform system testing
In-house RUNOFF
 test and run, verify specifications  Runn through SAT for potential problems
Go through punch list items
RUNOFF
 Runoff with customer acceptance Perform customer runoff
create customer punch list items
PHASE3 - INSTALLATION  
SHIPPING
 Use air ride trailor,   Un-assemble system and pack up
Load Truck
INSTALLATION
 Install equipment, power up, IO testing, reach points Unload Truck
Spot equipment to layout
Run all parts
execute commissioning
TRAINING
 Maintenance and Operator training  Perform Maintenance Training
Perfrom Operator Training
DOCUMENTATION
 EDOC & project documentation  Pass over all project data and transfer all warranties.
POST SALES
 New applications???  See if there are other oppertunities
 ff


















 







SAMPLE DOCUMENTATION
 

Project WorkSheet1
 

Robot Type
System Layout
Description
Part Information
EOAT

Project WorkSheet2
 

Project Management Tasks

Project Budget Etimates

Project Timeline Estimates

 
 
 

Project Schedule
 


MANAGE PROJECT CHANGES
DEFINE MILESTONES





 

RoboGuide Simulation
 

Robot Type
System Layout
Cycle Time Analysis
Reach Study
Program Development


 

 
   
 
   
   
   
   
 


PROJECT EXECUTION COMPARISSIONS

 

                        PAY ME NOW                                                                         PAY THEM LATER                                                
 Project Plan - Schedule, Task List, Details Project not on Schedule
 Engineering Approval  Debug on Site
 Risk Assessment - Safety Devices - DCS (Dual Check Safety)  Someone gets hurt or killed!
 Payload Schedules - Correct Payload data,   What's a payload schedule
 Project Simulation  We need a layout?  It goes where?
 Sucessful Runoff  Can't pass runoff - well fix it in the field
 Quick Installation - ON TIME   WITHIN BUDGET    TOTAL CUSTOMER SATISFACTION  Piss Poor Plan Prevents Proper Performance
 Project Documentation  What documentation
 Future Project Oppertunities  Look for New Customer
 ROI  +30%  ROI - 30%
   
   
   
   
   
   
   
   
   



Pre-Engineering

 
       


 

Engineering